Construction Drawings
Construction
Drawings including site and subdivision improvement plans, CIP projects,
revisions to approved improvement plans and reapprovals of expired
improvement plans, mass grade, sediment and erosion control, road layback,
common driveway, utility plans are routed with a due date of three
calendar weeks(excluding County holidays) from the date of
receipt.
Note: Second submissions are routed with
a due date of two calendar weeks(excluding County
holidays) from the date of receipt; all subsequent submissions are
routed with a due date of three calendar weeks(excluding
County holidays) from the date of receipt.
Engineering Modifications, Waivers and Supporting
Documents
Plans are routed with
a due date of two calendar weeks (excluding County holidays)
from the date of receipt.
Engineering Field Revisions
Plans are routed
with a due date of one calendar week(excluding County
holidays) from the date of receipt.
|